Environmental Service

Sögel – renaturation of a former municipal waste landfill site

  • Excavation of approx. 50,000 metric tons of municipal waste
  • Separating the waste using a mobile five-fraction sorting line
  • Construction time: approx. 12 weeks
  • Equipment PC 240, EC290, L70, L120, 2 mobile screening plants, 1 mobile air separator, 24 m mobile truck scales, DZ 750 wood shredder

Special features: constructing the infrastructure, organizing the logistics for removing approx. 2,500 metric tons/day. Area divided up into approx. 1 hectare of fill area and approx. 1 hectare of processing and storage area.